Skip to main content
File #: 25-608   
Type: Resolution (Consent) Status: Passed
File created: 12/5/2025 In control: Economic Development Commission
On agenda: 12/9/2025 Final action: 12/9/2025
Enactment date: 12/9/2025 Enactment #: 2025-405
Title: ADDED/ Commissioner Brown - EDC - To Appropriate General Fund Balance Toward the Construction of a Vehicular and Pedestrian Pass-through at 212 W. Main Avenue for $400,000
Sponsors: Chad Brown
Attachments: 1. Adopted 2025-405, 2. BCR, 3. Pass-through Project at 212 W. Main Ave

title

ADDED/ Commissioner Brown - EDC - To Appropriate General Fund Balance Toward the Construction of a Vehicular and Pedestrian Pass-through at 212 W. Main Avenue for $400,000

body

STAFF CONTACT

Donny Hicks - Economic Development - 704-829-2233

BUDGET IMPACT
budget

General Fund: Increase fund balance appropriation by $400,000. Increase operating expenditures by $400,000. This is a one-time investment to take place in FY2025.

body

BACKGROUND

In 2017, the property located at 212 W. Main Avenue, Gastonia, NC, was sold to CNB1920, LLC as an economic development project by the City of Gastonia. As part of this project, a vehicle and pedestrian pass-through will be constructed. To support the construction of this pass-through, which would provide public benefit to the citizens and visitors in the Downtown Gastonia area, the proposed appropriation of funding from Gaston County in the amount of $400,000.00 is requested.

 

The City of Gastonia has committed to financially supporting the construction of the pass-through, and staff recommends the approval of the Budget Change Request and authorization for the County Manager, or His Designee, to execute needed documentation to financially support the construction of said project.

POLICY IMPACT

Authorize the County Manager to execute necessary agreements to provide appropriated funding.