File #: 25-583   
Type: Resolution (Consent) Status: Agenda Ready
File created: 11/17/2025 In control: Office of Capital Improvements (OCI)
On agenda: 12/9/2025 Final action:
Enactment date: Enactment #:
Title: Commissioner Shehan - Office of Capital Improvements - To Appropriate Community Investment Funds and Award a Construction Contract to Classic City Mechanical in the Amount of $1,845,746.70 for the Old Willis Force Main Project and To Authorize the County Manager, or His Designee, to Execute Said Contract on Behalf of Gaston County
Sponsors: Scott Shehan
Attachments: 1. Adopted 2025-401, 2. BCR, 3. Bid Tabulation Old Willis Force Main
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Commissioner Shehan - Office of Capital Improvements - To Appropriate Community Investment Funds and Award a Construction Contract to Classic City Mechanical in the Amount of $1,845,746.70 for the Old Willis Force Main Project and To Authorize the County Manager, or His Designee, to Execute Said Contract on Behalf of Gaston County

 

body

STAFF CONTACT

 

Ray Maxwell - Executive Director of Capital Improvements - 704-862-7551

Kim Eagle, PH D - ARPA Director Water/ Sewer - 704-866-3102

 

BUDGET IMPACT
budget

 

Community Investment Fund: Appropriate $1,845,746.70 of fund balance. Increase transfers out by $1,845,746.70.

General Gov. Capital Fund: Increase transfers in by $1,845,746.70. Increase capital expenditures by $1,845,746.70.

 

body

BACKGROUND

 

The Old Willis Force Main Project came to fruition due to the necessity of adding capacity on the existing force main downstream of the pending Dallas High Shoals Regional Sewer Project at the current outfall to the Stanley Water Treatment Plant. The pipe size in the current state is an 8-inch line, and this project is planned to expand the capacity to 10 or 12 inches. The plan is to run a parallel force main alongside the existing pipe within the current confines of the established easement.

 

The project consists of installation of approximately 8,200 feet of new Force Main, base bid as 10 inches with an alternate as 12 inches. Includes one directional bore, approximately 700 feet under South Fork Catawba River.

 

The City of Gastonia has agreed to fund the cost to upsize the line from 10”-12”. The total cost of Gastonia’s portion is $272,049.49.

 

The Old Willis Force Main Project was publicly advertised, and the bids were received and publicly opened on November 25th, 2025. A total of 9 bidders submitted for the project with the results listed below. Classic City Mechanical submitted the apparent low, responsible bid in the amount of $1,845,746.70.

 

Contractor

Location

Bid Amount

Classic City Mechanical

Winterville, GA

$1,845,746.70  

Piedmont Utility Group

Mooresboro, NC

$1,934,211.17

Fuller & Co Construction, LLC

Crouse, NC

$1,972,153.70

Two Brothers Utilities, LLC

Shelby, NC

$2,446,204.78

Elite Infrastructure Group, LLC

Monroe, NC

$2,448,443.80

Timberline Construction Group, LLC

Pelham, AL

$2,497,939.00

Garney Companies, Inc

Apex, NC

$2,653,196.50

Dellinger, Inc.

Monroe, NC

$2,735,636.20

Sanders Utility Construction Group, LLC

Charlotte, NC

$2,965,610.23

 

Approval of this Board Action formally awards the project to Classic City Mechanical to perform the work, directs the County Attorney to draft all necessary contract documents, and authorizes the County Manager, or his Designee, to execute said documents for project implementation.

 

POLICY IMPACT

N/A

ATTACHMENTS

Budget Change Request (BCR), Certified Bid Tabulation